(another try) |
(format fixes) |
||
(One intermediate revision by the same user not shown) | |||
Line 14: | Line 14: | ||
*: ''28 May - Students informed yes/no about application'' | *: ''28 May - Students informed yes/no about application'' | ||
* June | * June | ||
*: Whole month - code, interact | |||
*: ''01 June - Project begins (depending on proposal)'' | *: ''01 June - Project begins (depending on proposal)'' | ||
{{admon/note|Proposals may have a modified schedule included.}} | {{admon/note|Proposals may have a modified schedule included.}} | ||
* July | * July | ||
*: ''5 July - Midterm evaluations period begins'' | *: ''5 July - Midterm evaluations period begins'' | ||
Line 30: | Line 30: | ||
*: 06 September - Sponsors release and deliver funds (proposed date) | *: 06 September - Sponsors release and deliver funds (proposed date) | ||
<pre> | |||
April 2010 May 2010 June 2010 | April 2010 May 2010 June 2010 | ||
Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa | Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa | ||
Line 36: | Line 37: | ||
11 12 13 14 15 16 17 9 10 11 12 13 14 15 13 14 15 16 17 18 19 | 11 12 13 14 15 16 17 9 10 11 12 13 14 15 13 14 15 16 17 18 19 | ||
18 19 20 21 22 23 24 16 17 18 19 20 21 22 20 21 22 23 24 25 26 | 18 19 20 21 22 23 24 16 17 18 19 20 21 22 20 21 22 23 24 25 26 | ||
25 26 27 28 29 30 23 24 25 26 27 28 29 27 28 29 30 | 25 26 27 28 29 30 23 24 25 26 27 28 29 27 28 29 30 ags | ||
30 31 | 30 31 | ||
Line 46: | Line 48: | ||
18 19 20 21 22 23 24 22 23 24 25 26 27 28 19 20 21 22 23 24 25 | 18 19 20 21 22 23 24 22 23 24 25 26 27 28 19 20 21 22 23 24 25 | ||
25 26 27 28 29 30 31 29 30 31 26 27 28 29 30 | 25 26 27 28 29 30 31 29 30 31 26 27 28 29 30 | ||
</pre> | |||
[[Category:Summer Coding 2010]] | [[Category:Summer Coding 2010]] |
Latest revision as of 03:16, 15 April 2010
This schedule is ready for Summer Coding 2010. Join the discussion mailing list and/or watch this page to be updated about schedule changes.
Start dates are emphasized and deadlines are in bold emphasis for student items.
- April
- 7 April - Students can begin submitting applications
- May
- Whole month - students, mentors, and sub-projects get to know each other
- 13 May - Mentors need to finish idea pages
- 20 May - Students applications + proposals need to be in
- 21 May - Sponsors must pledge funding by this point
- 24 May - Organizers finalize how many applications will be accepted
- 27 May - Mentors + admins finalize rank-ordered list
- 28 May - Students informed yes/no about application
- June
- Whole month - code, interact
- 01 June - Project begins (depending on proposal)
- July
- 5 July - Midterm evaluations period begins
- 12 July - Midterm evaluations due
- August
- 09 August - Project coding completes
- 16 August - Students final report, code snapshot, and evaluations due
- 20 August - Mentor evaluations due for students
- 23 August - Final evaluations due back to students
- 25 August - Mentor, sub-project evaluations due
- September
- 01 September - Sponsors receive report from organizers
- 06 September - Sponsors release and deliver funds (proposed date)
April 2010 May 2010 June 2010 Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa 1 2 3 1 1 2 3 4 5 4 5 6 7 8 9 10 2 3 4 5 6 7 8 6 7 8 9 10 11 12 11 12 13 14 15 16 17 9 10 11 12 13 14 15 13 14 15 16 17 18 19 18 19 20 21 22 23 24 16 17 18 19 20 21 22 20 21 22 23 24 25 26 25 26 27 28 29 30 23 24 25 26 27 28 29 27 28 29 30 ags 30 31 July 2010 August 2010 September 2010 Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa 1 2 3 1 2 3 4 5 6 7 1 2 3 4 4 5 6 7 8 9 10 8 9 10 11 12 13 14 5 6 7 8 9 10 11 11 12 13 14 15 16 17 15 16 17 18 19 20 21 12 13 14 15 16 17 18 18 19 20 21 22 23 24 22 23 24 25 26 27 28 19 20 21 22 23 24 25 25 26 27 28 29 30 31 29 30 31 26 27 28 29 30